On March 28th, the tracks of the eastern section of Qingdao Subway Line No. 2 (18 stations from Licun Park Station to Zhiquan Road Station) have been all paved. This is another milestone for the construction process of the subway line No. 2 following the tunnel has been dug up this January. It marks that the project construction focus will be transformed from civil engineering to the installation of mechanic and electronic equipment.
The Subway Line No. 2 is about 25km long in total and will set up 22 stations. As planned, the east section will be put into trial operation and open to traffic. ( By Fu Xuejun)